Construction firm · 2 conference rooms · 1 week · crew of 3Two empty rooms to fully working conference spaces in one week.
The situation: This client builds data centers for a living. Their own office had two empty conference rooms with no displays, no audio, no cameras, and no network infrastructure to support any of it. They needed both rooms meeting-ready.
What made it hard: The equipment was the easy part; the coordination wasn’t. The wrong speakers arrived, so we caught it on site and worked the replacement into the schedule. The job needed specialized cabling that wasn’t in the original plan, so we sourced it mid-project. And two IT teams were involved, ours and the client’s, so every connection and handoff had to be agreed by both sides before the rooms went live.
The work: We installed 4 displays plus ceiling speakers, cameras, and microphones across both rooms; built out 2 network racks; pulled and terminated the Cat6 network and AV cable runs; and tested every room end to end before handoff.
The result: Two fully working conference rooms in one week, with the surprises handled on site instead of handed back to the client.